I just finaled animation on the sixth of the films nine sequences- sequence seven is already %87 complete and sequence eight is %48 complete. I'll have both of those done by the 23rd of this month then its on to the films final sequence. Since the films final sequence has so much complex animation in it- I'm going to lower my quota to 8 shots/day for this sequence- for the rest of the film its been from 10-20 shots/day
Post production schedule for I am Nightmare
Post production schedule for I am Nightmare
Post production schedule for I am Nightmare
I just finaled animation on the sixth of the films nine sequences- sequence seven is already %87 complete and sequence eight is %48 complete. I'll have both of those done by the 23rd of this month then its on to the films final sequence. Since the films final sequence has so much complex animation in it- I'm going to lower my quota to 8 shots/day for this sequence- for the rest of the film its been from 10-20 shots/day